Widtmann und Blume

Stolberg

Open today

Diepenlinchen Drainage Shafts

Since dewatering the mine had been a problem from the very beginning due to inflows averaging 9,000 liters per minute, a more cost-effective dewatering solution became necessary in 1855. That year, engineer Widtmann—after whom the Widtmann Shaft was named—designed a 2.4-kilometer-long drainage adit intended to divert mine water from a depth of 88 meters (corresponding to the elevation of the Vicht Valley) into the Vicht River. Since the mine had already been sunk to a depth of 159 meters by that time (1854), the water had to be pumped up only 71 meters. Work on driving the tunnel began in 1857, and sinking of the Widtmann Shaft began in 1855. The shaft had a fairly large cross-section of 5.65 m x 3 m, as it had to accommodate two pumping rods. The reason for this was that the corresponding pumping systems were constantly subjected to heavy loads, but water still had to be pumped out even while they were being maintained; for this reason, they were always serviced alternately. Furthermore, as the depth increased, the drainage shaft had to be driven deeper and deeper without interrupting the pumping of mine water. Neither of the shafts (Widtmann and Blume) was sunk into the water-bearing limestone (since they would otherwise have flooded during construction), but rather into the shale immediately adjacent to it, which did not contain water and could therefore be driven down relatively easily.

The Widtmann shaft was lined with bricks down to a depth of 150 m to ensure structural stability. As the depth increased, it became necessary to drive a second dewatering shaft, so work on the Blume shaft began in 1866. The shaft was named after Blume, the mine director at the time, and had a cross-section of only 2.5 m x 3.9 m; it was also lined only with bolted timber framing. Mine water was pumped out of both shafts using two steam engines, which in 1900 had a combined output of 2,000 PS and consumed 12,541 metric tons of coal. In 1912, a depth of 382 m was reached at the pump sump on the deepest level, making both shafts the deepest in the entire Stolberg coalfield. After the mine was closed, the shafts were not backfilled, as this would have jeopardized drainage through the dewatering tunnel.

This would have resulted in unforeseeable mining damage. Instead, both shafts were covered with concrete slabs, and a small building was erected above the Widtmann shaft to allow for inspection of the drainage system. Both fell increasingly into oblivion until, during construction work in 2006, both shafts were uncovered and subsequently professionally sealed with a reinforced concrete slab each. Today, residential buildings stand above the shafts, and the dewatering tunnel continues to drain the mine waters from Diepenlinchen through the tunnel entrance opposite the lead smelter.

This route was developed as part of the LEADER-funded project “Quality Initiative for Hiking in Roetgen and Stolberg” with support from the European Union (EAFRD) and the state of North Rhine-Westphalia.

Impressions

  • The image shows the symbol of the European Union and the coat of arms of North Rhine-Westphalia. It indicates co-financing by the European Union.
  • A construction site with a deep, empty trench and broken bricks. In the background, a gray wall of a building is visible.
  • A excavated plot with a concrete foundation. Raised earth layers lie around the foundation.
  • A deep shaft made of bricks that leads into the ground. The surrounding ground is uneven and shows earthworks.
  • A dark room with rusty pipes and a faint light. In the background, a large, round structure is visible.
  • A dark tunnel with discolored walls and loose stones on the floor. The surroundings appear mysterious and eerie.
  • A dark shaft with steep walls and few visible steps. The floor is covered with loose material.
  • A deep shaft with steep walls and a barrel-shaped background. The floor is covered with dust and small plants.
  • A deep well with calm, stony walls. The view leads into the darkness of the shaft.

Contact